Strengthening our Community
As you know, we’ve been working diligently to enhance your experience. Our original plans for the Base Lodge Expansion were met with challenges due to rising construction costs. We are now committed to delivering a project that meets your needs and aligns with our club’s vision.
Our revised plan focuses on delivering the core elements of our original vision, while staying within budget. We’re excited to share the key features of this project:
- Expanded Seating: 300 additional seats for members to relax, socialize, and enjoy the club's amenities.
- Enhanced Kitchen: Improved kitchen facilities to better serve our membership
- Adult Lounge: A dedicated space for adults to unwind and socialize.
- Increased Family Lockers: More convenient storage for your belongings.
- Main-Floor Washrooms: Improved accessibility and comfort.

Frequently Asked Questions
Needs and Priorities
Declining interest rates, stabilized construction costs, and reduced local activity make this a financially optimal time to proceed. The club’s strong economic position supports the investment, while the Base Lodge kitchen and South Lodge require urgent upgrades. Delaying would risk higher costs and further competitiveness loss as neighbouring clubs. The BLE ensures our club remains modern, functional, and a leader in the region.
Design and Functionality
The outdoor ski locker building will remain for at least one more ski season and will be reimagined in the future as part of long-term facility improvements.
Communication and Member Engagement
Regular updates will be shared via emails, newsletters, and member meetings. A comprehensive information package will be available on the website before the February vote.
Member surveys and listening sessions have shaped the project, and ongoing feedback will continue to be encouraged.
Voting will occur electronically through Simply Voting with results shared transparently through all club communication channels. Voting will open at the conclusion of the Town Hall on February 16th and remain open for seven days.
The club management aims for 100% voter turnout by providing clear communication, detailed information, and hosting member engagement events to answer questions and address concerns.
The South Lodge will be removed in April 2025. A farewell event is being planned to celebrate its history, followed by a well-organized transition to construction activities.
Operational and Logistical Impacts
The timeline for the BLE is as follows:
- April 2025: Begin construction and remove the South Lodge.
- Late 2025 – March 2026: Pause construction during the ski season to minimize disruption.
- April 2026: Resume construction.
- November 2026: Complete construction and open the expanded facilities. Efforts will minimize operational disruptions, including providing temporary facilities for impacted areas.
Temporary facilities for locker rooms and seating will be provided. Squires Johns will relocate to a trailer during construction.
Yes, the food service areas will be reconfigured and expanded to improve flow and capacity, meeting member needs during peak times.
Governance and Oversight
The Board has established a dedicated Base Lodge Expansion (BLE) construction team which will provide monthly reports to the Board of Directors. The General Manager is taking on the overall responsibility for this build and will be in contact communication with the building committee of the Board. to ensure the project adheres to its goals and timeline. The Club is committed to maintaining excellent communication with members by providing regular updates, sharing detailed financial information, and hosting Q&A sessions.
Contractors were selected based on their experience, reliability, and competitive pricing. Over 75% of hard costs have already been quoted.
The timeline includes clear milestones, and the 10% contingency ensures financial flexibility. The Board’s oversight will maintain adherence to the schedule and budget.
The 50-year capital plan ensures the BLE fits into the broader strategy, balancing current improvements with long-term sustainability.
When the original Base Lodge was built in 2004, the club incurred $2.5 million in debt to complete the project. This was a significant investment at the time, reflecting the club’s commitment to providing a high-quality facility for its members. The Debt that the proposed BLE would encounter is $2-4M, a modest sum on a relative basis.
Maintaining the Old South Lodge in a functional state over the next 15 years is estimated to cost approximately $5 million. This estimate is based on wear, damage, and conditions that WSP Canada Inc. was able to see and inspect during their assessment. These costs would include necessary upgrades, repairs, and ongoing maintenance to ensure the facility remains operational in it’s current configuration. There would be an additional cost of approximately $1 million to repurpose and renovate existing spaces as well as $2 million to renovate and expand the Base Lodge Kitchen. However, this significant financial commitment underscores the importance of considering the Base Lodge Expansion, which would not only eliminate the need for continued investments in the aging South Lodge but also provide modernized and consolidated facilities to better meet the needs of the Craigleith community.
As part of Project Generations, $4.5 million was collected through an assessment, and these funds were fully used in the construction of the Depot. While the original Project Generations plan included a borrowing of $8 million, this borrowing was not utilized for the Depot. The Depot’s total cost of $10 million was covered using the collected assessment funds, Capital Levy, and new member initiation fees. For the upcoming Base Lodge Expansion (BLE) project, the anticipated debt is projected to range between $2 million and $4 million, depending on when the Little John chairlift is replaced.
If the membership declines the Board’s proposal, the South Lodge will still be removed, leaving the club to operate within the existing spaces without any of the planned enhancements. This would mean no additional seating to offset the loss of the South Lodge, no adult lounge, and no expanded kitchen space to improve food services. Furthermore, there would be no increase in the number of lockers, which are needed to address current and future member requirements. Squire Johns would also have to be moved outdoors again, as there would be no provision for an indoor space during or after the transition. The lack of these upgrades would strain the existing facilities, reduce convenience for members, and limit the club’s ability to adapt to growing needs. Moreover, it could impact the club’s ability to attract new members, as the facilities may no longer align with the expectations of prospective families or individuals seeking a modern and accommodating club environment.
Featured Videos

Investing in Our Community
Stay Tuned for More
As the project progresses, we’ll keep you informed through dedicated updates in the Club Bulletin, on our website, and at in-person member meetings. You’ll have opportunities to learn more about the project, including the latest timelines, design details, and how it will enhance your club experience. Your input is invaluable to us as we work to create a space that meets the needs of our members.